Microsoft Project Cuts Bunglai Road Reconstruction Delay by Four Weeks

Illustration by Ai


The Bunglai Road Reconstruction Project in Banjar Regency, South Kalimantan, was projected to finish in January 2026. However, researchers found that integrating Microsoft Project with the Earned Value Method (EVM) could accelerate completion by four weeks, allowing the project to finish in mid-November 2025. The study was conducted by Rizka Aprilia and H. Muhammad Humaidi from Banjarmasin State Polytechnic (Politeknik Negeri Banjarmasin) and published in the International Journal of Integrative Research (IJIR) in 2026. The findings demonstrate how data-driven project management can improve construction efficiency while keeping costs under control.

Road infrastructure plays a vital role in regional economic development by improving mobility, logistics, and public safety. The Bunglai Road is part of the Banjarbaru–Batulicin alternative route and has long been recognized as a high-risk accident location due to its sharp horizontal curves and steep mountainous terrain. To address these safety concerns, the South Kalimantan Provincial Government initiated a major reconstruction project aimed at improving the road’s geometric design and overall driving safety.

Despite its strategic importance, the project encountered significant implementation challenges. Critical activities—including earth excavation, rock excavation, and aggregate pavement construction—fell behind schedule because of difficult topography, heavy rainfall, and repeated mechanical failures of heavy equipment. As delays accumulated, both project duration and operational costs became increasingly difficult to manage.

A Data-Driven Approach to Project Control

Aprilia and Humaidi analyzed the project using contract documents, the cost budget plan, S-curve scheduling data, weekly progress reports, and actual expenditure records. The reconstruction project had a contract value of approximately IDR 23.08 billion and a planned duration of 180 calendar days, equivalent to 19 weeks.

The researchers rebuilt the project schedule in Microsoft Project to identify critical activities and simulate alternative scheduling scenarios. They then applied the Earned Value Method (EVM), a project management technique that compares planned work, completed work, and actual spending to evaluate both schedule and cost performance throughout construction.

This combination enabled the researchers to detect project deviations early and estimate future financial and scheduling risks before they became irreversible.

Delays Reached Their Peak in Week 13

The analysis revealed that the project entered its most critical phase during the middle of construction. By Week 13, actual physical progress had reached only 60.10%, while the planned cumulative progress was 80.71%. This represented a negative schedule deviation of 20.61%, indicating that major construction activities had fallen substantially behind the baseline schedule.

Performance indicators also reflected deteriorating project conditions. The Schedule Performance Index (SPI) remained below 1.0 from Week 2 through Week 17, confirming continuous delays. Meanwhile, the Cost Performance Index (CPI) dropped below 1.0 beginning in Week 11 and again during Weeks 13–17, signaling that actual project expenditures had started exceeding the value of completed work.

The worst financial performance occurred in Week 17, when the project recorded a Cost Variance of approximately minus IDR 1.97 billion. According to the researchers, this loss was largely driven by idle heavy equipment rental costs and uncoordinated acceleration efforts implemented in the field.

Rescheduling Reduced the Project Duration

To overcome these challenges, the research team developed a comprehensive rescheduling strategy using Microsoft Project. The revised plan included adding two excavator units, introducing night-shift operations on critical activities, and changing several sequential work relationships into overlapping tasks through a fast-tracking approach.

The simulation produced remarkable improvements. The total project duration decreased from 19 weeks to 14 weeks, shifting the projected completion date from January 2026 to mid-November 2025.

Cost performance improved as well. After rescheduling, the CPI ranged between 1.39 and 3.74, while the SPI remained between 1.00 and 1.51 until physical construction reached 100 percent completion in Week 14. These values indicate that the project would not only progress faster than planned but also operate more efficiently within the available budget.

Why These Findings Matter

The study offers practical insights for infrastructure projects built in geographically challenging environments. Rizka Aprilia and H. Muhammad Humaidi argue that integrating Microsoft Project with the Earned Value Method provides contractors, consultants, and government agencies with a comprehensive monitoring system that combines schedule, physical progress, and financial performance into a single decision-making framework.

The researchers emphasize that early detection of schedule and cost deviations allows project managers to prioritize critical activities, optimize heavy equipment utilization, and implement corrective actions before delays escalate into substantial financial losses.

For future road construction projects, they recommend maintaining standby heavy equipment from the beginning of construction and adopting EVM-based reporting as a standard monthly monitoring system for public infrastructure projects.

Author Profiles

Rizka Aprilia is a civil engineering researcher at Banjarmasin State Polytechnic (Politeknik Negeri Banjarmasin), specializing in construction management, project scheduling, and cost control for infrastructure development.

H. Muhammad Humaidi is a lecturer and researcher at Banjarmasin State Polytechnic, with expertise in civil engineering, project management, and construction performance evaluation using the Earned Value Method. He also serves as the corresponding author of this publication.

Research Source

Article Title: {turn0file0.title}

Authors: Rizka Aprilia & H. Muhammad Humaidi

Affiliation: Banjarmasin State Polytechnic (Politeknik Negeri Banjarmasin)

Journal: International Journal of Integrative Research (IJIR), Vol. 4, No. 7, 2026, pp. 577–592

DOI: 10.59890/ijir.v4i7.227

 


Posting Komentar

0 Komentar